In February 2023, Vietnam Electricity (EVN) ensured a safe and continuous power supply, serving socio-economic development and meeting the people's daily needs. At the same time, EVN successfully completed the water discharge for the Winter-Spring crop 2022-2023 for the Northern Delta provinces.

In February 2023, Vietnam Electricity (EVN) ensured a safe and continuous power supply, serving socio-economic development and meeting the people's daily needs. At the same time, EVN successfully completed the water discharge for the Winter-Spring crop 2022-2023 for the Northern Delta provinces.

In February 2023, the electricity output of the whole system reached 20.22 billion kWh, up 9.4% over the same period in 2022. However, accumulated in the first 2 months of the year, the electricity output of the whole system reached 38.61 billion kWh - down 2.2% over the same period. The mobilizing ratio of some types of power sources to the total electricity output of the whole system is as follows:

+ Hydropower reached 10.57 billion kWh, accounting for 27.4%.

+ Coal thermal power reached 16.47 billion kWh, accounting for 42.7%.

+ Gas turbines reached 4.32 billion kWh, accounting for 11.2%.

+ Renewable energy reached 6.45 billion kWh, accounting for 16.7% (of which solar power reached 3.87 billion kWh, wind power reached 2.4 billion kWh).

+ Imported electricity reached 735 million kWh, accounting for 1.9%.  

Power transmission output in February 2023 reached 16.1 billion kWh. Accumulated in 2 months of 2023, transmission power output reached 30.53 billion kWh, up 0.2% over the same period last year.

Construction investment: (i) Regarding power source: continue to focus on the construction of Expansion Hoa Binh and Expansion Ialy hydropower projects, Quang Trach 1 thermal power plant. Particularly, the Expansion Tri An hydropower project is currently waiting for the approval of the project investment policy by the competent state management agencies and the Dong Nai Provincial People's Committee. Bac Ai pumped-storage hydropower project is continuing to complete the technical engineering of phase 2. (ii) Regarding the power grid: in the first 2 months of 2023, EVN and its units have commenced 07 projects and completed energizing and putting into operation 11 power grid projects from 110kV to 500kV.

Digital transformation: By the end of February 2023, units throughout EVN have completed 97.18% of the digital transformation implementation plan, in which the fields of business and customer service and construction investment have been basically completed 100%, some fields have been completed with a high rate such as internal administration (99.93%), production (96%).

Regarding the financial situation, due to the sudden increase in input fuel prices for electricity production since the beginning of 2022, while the retail electricity price has remained unchanged since 2019 until now, EVN's financial situation has faced many difficulties and does not ensure financial balance.

Some working tasks of EVN in March 2023

In March 2023, the average daily power consumption of the whole system is expected at 743.5 million kWh/day. System operation objectives: Continue to ensure the power production and supply for production - business activities and people's daily life. Thoroughly save multi-purpose hydropower, exploit the remaining hydropower plants in the direction of optimal regulation in the operation plan, and meet the constraints of the power grid/system demand and downstream water supply requirements. For coal-fired power plants and gas turbines: Highly mobilize coal-fired power plants and gas turbines to save water in hydropower reservoirs; mobilize according to the demands of the system of imported coal plants, ensuring the constraints against grid overload and voltage quality. At the same time, in order to reduce difficulties in power system operation in the dry season months of 2023, EVN continues to advise people, offices and production facilities to pay attention on using electricity safely and economically, etc.

Regarding construction investment: in March 2023, EVN and its units focus on reviewing the implementation plan of key grid projects; urgently energizing Bo Y switch-off station and its connection, expanding Phuoc Thai 220kV substation and its 110kV connection lines; energizing 220kV bays at the switch yard of Trung Nam Power Plant, putting into operation Ninh Phuoc - Thuan Nam 220kV transmission line, etc.

Other activities: Prepare to deploy events and communication activities in response to the Earth Hour 2023 campaign, and implement Youth Month activities on the occasion of the 92nd anniversary of the Ho Chi Minh Communist Youth Union.

CONTACT INFO:

Communication Department - Vietnam Electricity Corporation;

Address: No.11 Cua Bac Street, Truc Bach Ward, Ba Dinh District - Hanoi;

Email: bantt@evn.com.vn ; Tel: 024.66946405/66946413;           

Website: www.evn.com.vnwww.tietkiemnangluong.vn

Fanpage: www.facebook.com/evndienlucvietnam

Youtube: https://www.youtube.com/c/ĐIỆNLỰCVIỆTNAM_EVNnews

Tiktok channel: https://www.tiktok.com/@dienlucvn

Another news

PM sets higher requirements for 500 kV Lao Cai – Vinh Yen transmission line project

The 500 kV Lao Cai – Vinh Yen transmission line is a strategic national infrastructure project approved by the Government, with Vietnam Electricity (EVN) as the investor. The double-circuit transmission line will span 229.5 kilometers, with 468 tower foundations across the four northern provinces of Lao Cai, Yen Bai, Phu Tho, and Vinh Phuc. The total investment for the project is over 7.41 trillion VND (290.41 million USD).

Operational situation in February 2025 and objectives and tasks in March 2025

In February and the first 2 months of 2025, Vietnam Electricity and its member units ensured power supply for the country's socio-economic development and people's needs. In particular, EVN successfully completed the water discharge and ensured power supply for pumping stations and in-field pumps operating to serve the 2024-2025 Winter-Spring rice cultivation in the Northern Midlands and Delta provinces.

Operational situation in October 2024; objectives and tasks in November 2024

In October 2024, Vietnam Electricity and its member units ensured sufficient power supply for the country's socio-economic development and people's needs in the context of continued high electricity demand growth. In particular, EVN units in the Central region proactively responded to and remedied the consequences of storm No. 6 (Tra Mi).

Operational situation in first 9 months and objectives and tasks for quarter IV of 2024

In the first 9 months of 2024, economic growth continued to restore and maintain positive development momentum in all 3 regions (agricultural production; industrial production; trade - services) leading to high demand for electricity, the power supply situation in the peak months of the dry season in 2024 faced many challenges. In addition, the development of natural disasters and floods also greatly affected the power supply ensuring, especially the impact of storm No. 3 (Yagi) and post-storm flooding in 26 provinces/cities in the Northern region. However, with the strong and regular direction of the Government, the Prime Minister, ministries, branches, and localities, together with the solidarity, efforts, and determination of the leadership and all employees, the task implementation in the first 9 months of 2024 of EVN has achieved many remarkable results.

Performance in July 2024, targets and tasks in August 2024

In July 2024, Vietnam Electricity (EVN) continued to ensure a safe and stable power supply, serving socio-economic development, and meeting people's daily needs, in the context of continuously increasing electricity demand and during the month with storms, tropical depressions, heavy rains, and floods occurring in many areas in the Northern mountainous region, affecting power supply as well as some power grid projects. The total electricity output of the system in July 2024 reached 27.7 billion kWh, an increase of 6.9% over the same period in 2023. Of which: the largest daily electricity consumption (July 9) reached 964.3 million kWh and the maximum capacity reached 46,298MW (on the same day of July 9).

Operational situation in first 6 months of 2024; objectives and tasks in July and remaining months of 2024

In the first 6 months of 2024, Vietnam Electricity has ensured a safe and stable power supply, serving socio-economic development, and meeting the people's daily needs, in the context of continuously increasing power demand. EVN's management and operation of the power system and electricity market have followed the approved plan closely.