GENCO 3 Press Release

SITUATION OF PRODUCTION, BUSINESS, INVESTMENT AND CONSTRUCTION IN NOVEMBER AND TARGETS, TASKS AND PLANS IN DECEMBER 2021

During the month, power plants of EVNGENCO3 have successfully satisfied the mobilization of the National Load Dispatch Centre, ensured the safe and continuous power supply. EVNGENCO3's power output in November 2021 is 2,441 billion kWh, reaching 88.75% of the plan. However, the load demand of the power system continues to be low due to the effects of the COVID-19 pandemic. Hydrological conditions are favorable, so plants of Buon Kuop Hydropower Company have mobilized on the basis of water flows.

SITUATION OF PRODUCTION, BUSINESS, INVESTMENT AND CONSTRUCTION IN THE FIRST 9 MONTHS OF 2021 AND TARGETS, TASKS AND PLANS IN OCTOBER 2021

EVNGENCO3's power output in September 2021 is 2.067 billion kWh, reaching 77.73% of the plan. The accumulated output in the first 9 months of 2021 is 22.562 billion kWh, reaching 68.98% of the year plan.

SITUATION OF PRODUCTION, BUSINESS, INVESTMENT AND CONSTRUCTION IN 2020 AND TARGETS, TASKS AND PLANS IN 2021

The generated power output in 2020 of EVNGENCO 3 is 33.254 billion kWh, of which, the accumulated output is 31.103 billion kWh, reaching 100.1% of the plan.

PRODUCTION, BUSINESS AND CONSTRUCTION INVESTMENT SITUATION IN THE FIRST 6 MONTHS AND TARGETS, TASKS AND PLANS FOR THE LAST 6 MONTHS OF 2020

The power output in June 2020 of EVNGENCO 3 is 2,925 billion kWh, the accumulated output in the first 6 months of 2020 is 17,061 billion kWh, reaching 48.25% of the year plan because the power grid’s additional charges decreased sharply due to impacts of the Covid-19 epidemic.

PRESS RELEASE – COMPLETING TRIAL INSTALLATION OF MÃI XANH’S 3 ADOBE BRICK PRODUCT LINES

On 27/11/2017, the delegation includes Mr. Luong Van Hai – Vice Chairman of People's Committee of Binh Thuan province, Mr. Nguyen Tai Anh – Vice President  of Vietnam  Electricity, representatives of provincial departments, Power Generation Corporation 3 came to check and witness 3 completed lines of the trial production operation of adobe brick from ash of Vinh Tan 2 Thermal Power Plant .