At 23:45 a.m. on July 31, 2020, after 31 days of downtime (from July 1st to July 31st, 2020), plant units of the Phu My 4 Thermal Power Plant were officially handed over to the National Load Dispatch Centre (A0) for putting into operation, after completing the overhaul as planned. This is the first time units have performed the repair of GT41 and ST43 plant units, 41 and 42 furnaces without the direct assistance of the GE’s manufacturing experts at the Site.