Vinh Tan 4 Extension Thermal Power Plant is one of the imperative projects to address the power shortage in the South from 2020 of the Government. The project is owned by EVN and EVNGENCO 3 involves in as a project management consultant.
Total investment of the project to be VND 23,000 billion with total installed capacity of 600 MW (1x 600MW), a production capacity of 3.6 billion kWh per year. This project is of great significance, marking a new development step for Vietnam's electricity industry with some outstanding features such as being the coal fired power plant using huge number of quantity of coal, being the first power plant using the super-critical technology,
This project is playing a significant role with the high proportion of local involvement and being the first large-scale thermal power plant designed by the Vietnam consulting agency.